NU Jacobs Generator Switchover

Scheduled Maintenance Report for Northwestern Information Technology

Completed

The scheduled maintenance has been completed.
Posted Apr 09, 2026 - 12:00 CDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 09, 2026 - 07:30 CDT

Scheduled

Northwestern University IT will be switching over from a temporary generator at the Jacobs Center to a permanent generator in coordination with the NU electrical shop. During this maintenance, repairs will also be made to the Jacobs Center UPS communications card.
Posted Apr 07, 2026 - 14:37 CDT
This scheduled maintenance affected: Infrastructure (Electrical Systems (Data Center Facilities)).